Current Projects

Item Project Title Client Project Value (RM) Start Completed
1 Supply, Fabricate and install Keel Blocks at Masai, Johor Malaysia Marine And Heavy Engineering Sdn Bhd
1,088,000.00
02.09.2019 01.03.2020
2 Road Repair at Jalan MMHE 1& 7, MMHE Pasir Gudang, Johor. Malaysia Marine And Heavy Engineering Sdn Bhd
263,833.50
06.09.2019 30.12.2019
3 Proposed U Drain And Pre-Feb Drain at Skid Track, fabrication Area No.4 Malaysia Marine And Heavy Engineering Sdn Bhd
495,583.20
23.09.2019 05.02.2020
4 Proposed U Drain at Skid Track Area No.6 Malaysia Marine And Heavy Engineering Sdn Bhd
50,170.00
19.11.2019 30.12.2019
5 EPCC Of Pengerang Centralised Tankage Facilities(PCTF) At pengerang, Johor. Dialog E & C Sdn Bhd
32,245,135.46
23.9.2019 17.07.2020